Timeline, if Project Moves Forward.
Timeline may be extended but time available for parish review will not change.
9/13/20 Completion of architects’ concept plan for SAEC review.
9/30/20 Vestry decision on signing non-binding MOU.
10/30/20* Shared use agreement signed.
10/30/20* Shared space agreement signed.
11/27/20* Lease option agreed and signed.
2/1/21 Submission of LIHTC application. Further actions will depend upon
acquisition of corner lot and award of tax credits.
*, means and estimated date.